... Section No. 2 , $ 10,000 . To Seventh Avenue Construction Co. , signal tower and battery room , 34th Street station ... Section No. 2 , $ 25,000 . To J. H. Burton & Co. , Inc. , wooden piles , Routes Nos . 19 and 22 , Section No. 2 ...
... Section No. 2 , $ 10,000 . To Seventh Avenue Construction Co. , signal tower and battery room , 34th Street station ... Section No. 2 , $ 25,000 . To J. H. Burton & Co. , Inc. , wooden piles , Routes Nos . 19 and 22 , Section No. 2 ...
Էջ 188
... Section No. 1.- This section includes most of the so - called Diagonal Station , the connecting link between the new subway on Lexington avenue and the existing Manhattan- Bronx Rapid Transit Railroad under Park avenue , and extends ...
... Section No. 1.- This section includes most of the so - called Diagonal Station , the connecting link between the new subway on Lexington avenue and the existing Manhattan- Bronx Rapid Transit Railroad under Park avenue , and extends ...
Էջ 192
... section . Considerable backfill has been placed and temporary pavements laid over same . Route No. 5 , Section No. 13.- The subway structure was sub- stantially completed in 1916. Since that time the contractor has been engaged in the ...
... section . Considerable backfill has been placed and temporary pavements laid over same . Route No. 5 , Section No. 13.- The subway structure was sub- stantially completed in 1916. Since that time the contractor has been engaged in the ...
Էջ 193
... Section No. 1. - There were 290 linear feet of sewer constructed during the year , making a total of 2,520 linear feet built to December 31 , 1917 , amounting to 95 per cent of the total sewer work on this section . Route No. 5 , Section ...
... Section No. 1. - There were 290 linear feet of sewer constructed during the year , making a total of 2,520 linear feet built to December 31 , 1917 , amounting to 95 per cent of the total sewer work on this section . Route No. 5 , Section ...
Էջ 200
... Section No. 1.- The construction work on this section for the main subway structure and the stations has been practically completed ; the Brook Avenue station and the short stretches south of 139th street and at 142d street , which ...
... Section No. 1.- The construction work on this section for the main subway structure and the stations has been practically completed ; the Brook Avenue station and the short stretches south of 139th street and at 142d street , which ...
Այլ խմբագրություններ - View all
Common terms and phrases
application approval Avenue line Avenue station Bills rendered Bklyn bonds bridge Broadway Bronx Brooklyn Heights Railroad Brooklyn Union Gas cars cent City Closed Commission issued Commissioner company and service completed Coney Island connection Consolidated Gas Co construction contract dated December disclose any error Discontinuance dismissed District Elec Elevated line equipment error in bills extension filed Fulton Street Gas Company grade crossing Hearing Resolution hereby installed Interborough Rapid Transit Investigated by Transit Investigation failed Island Railroad Company January July June Long Island Railroad Manhattan Matter taken meter N. Y. Cons Nassau Electric Nassau Electric Railroad operation Overindexing pany passengers proceeding was begun Public Service Commission Railway Company Rapid Transit Company rendered for gas Rockaway Route satisfied schedule Section sewer Shown upon investigation steel Street station Third Avenue Third Avenue Railway tion tracks trains Transit Bureau tricity tunnel York Central Railroad York Consolidated Railroad York Edison York Municipal Railway