Plumbing Estimates and ContractsStandard sanitary mfg. Company, 1910 - 203 էջ |
Այլ խմբագրություններ - View all
Common terms and phrases
acceptance advertising agreement allowance amount of pipe Angle Valves architect August Blank average bath room bath tub bills branch building catalogue cent charged clause complete condition consideration contract crating damages day's Diameter dollars drawings drayage Earthenware Elbows equals estimate blank extra heavy figure fixtures floor free on board freight furnish Inches Inches installation instance iron pipe Iron Pipe Sizes jobbers jobbing house joints lavatory layout lead pipe length of pipe liquidated damages list price multiplied loss material and labor oakum outlets owner parties payment percentage pipe and fittings plans and specifications plumber plumbing contractor pounds profit purchaser Return Bends roughing-in scale secure sheet lead shown in Fig signed sizes soil pipe solder stack Statute of Frauds Straight and Reducing supply houses Table taking off quantities timator tion toilet rooms tract trench various water closet workmen Wrought Pipe
Սիրված հատվածներ
Էջ 188 - It is also understood and agreed by and between the parties hereto that such additional drawings and explanations as may be necessary to detail and illustrate the work to be done are to be furnished by said Architect, and they agree to conform to and abide by the same so far as they may be consistent with the purpose and intent of the original drawings and specifications referred to in Art.
Էջ 189 - Contractor , then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all...
Էջ 188 - It Is understood and agreed by and between the parties hereto that the work Included In this contract is to be done under the direction of the said Architect, and that his decision as to the true construction and meaning of the drawings and specifications shall be final.
Էջ 190 - It is further mutually agreed between the parties hereto that no certificate given or payment made under this contract, except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials.
Էջ 188 - No alterations shall be made in -the work except upon written order of the architect; the amount to be paid by ' the Owner or allowed by the Contractor by virtue of such alterations to be stated in said order.
Էջ 190 - ... against such lien or claim. Should there prove to be any such claim after all payments are made, the Contractor shall refund to the Owner all moneys that the latter may be compelled to pay in discharging any lien on said premises made obligatory in consequence of the Contractor's default.
Էջ 189 - Should the Contractor be delayed in the prosecution or completion of the work by the act, neglect or default of the Owner , of the Architect , or of any other contractor employed by the Owner upon the work, or by any damage caused by fire or other casualty for which the Contractor...
Էջ 189 - Should the Contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the Architect, the Owner shall be at liberty, after three days...
Էջ 188 - Architects shall by like written notice condemn as unsound or improper, or as in any way failing to conform to the drawings and specifications.
Էջ 190 - The final payment shall be made within days after the completion of the work included in this contract, and all payments shall be due when certificates for the same are issued.