Page images
PDF
EPUB

Opinion of the Court.

270 U.S.

MR. JUSTICE STONE delivered the opinion of the Court.

This appeal was taken from a judgment of the Court of Claims (Jud. Code, § 142, before its repeal by Act of February 13, 1925,) dismissing appellant's petition and adjudging that the United States was entitled to recover on a counterclaim set up in its answer in that court.

The appellant entered into a contract with the Government, dated June 24, 1918, to supply it with a quantity of cloth at a specified price. It was provided by the contract that the Government might, in the event of the termination of the war, cancel the contract with respect to cloth not delivered. The contract contained a clause for ascertaining the balance due and payable to the appellant in case of cancellation. By a second contract, of July 6, 1918, the Government undertook to advance money to appellant for the purchase of machinery, equipment and raw material required for the performance of its original contract. Appellant gave its demand note for the principal sum advanced, with interest at 6%, and it was provided by the contract that specified deductions from payments, as they became due from the Government for the cloth delivered, should be credited on the note.

On November 15, 1918, the Government cancelled the original contract after 19.02% of the deliveries stipulated for had been made. Appellant presented a claim to the War Department for the amount due under this contract, and, after proceedings had before the Purchase Claims Board, and an appeal to the Board of Contract Adjustment, an award was made to appellant, by authority of the Secretary of War, in the sum of $14,054.59, which was stated by its terms to be "in full adjustment, payment and discharge of said agreement" of June 24, 1918.

On June 3, 1920, appellant accepted the award by a formal statement to that effect written at the end of it and signed by the appellant, by its treasurer.

375

Opinion of the Court.

The cause of action stated by appellant is upon its first contract, of June 24, 1918, and, as the Court of Claims found, all of the items set up by appellant in this suit were embodied in its claim to the War Department on which the award was made. The Government pleaded, by way of counterclaim, the balance due upon the appellant's promissory note, less the amount of the award; and judgment was given against the appellant for this amount, with accrued interest.

Appellant, notwithstanding such cases as United States v. Adams, 7 Wall. 463; Savage, Executrix, v. United States, 92 U. S. 382, 388; United States v. Child & Co., 12 Wall. 232, 243; United States v. Justice, 14 Wall. 535; Mason v. United States, 17 Wall. 67, seeks to avoid the effect of the accepted award by setting up that the Secretary of War was without authority to make it and, upon various technical grounds, that appellant's acceptance was not binding.

It is unnecessary for us to consider these contentions; for there are no findings by the Court of Claims that appellant suffered any loss or damage by reason of the cancellation of the contract, and in fact, no findings which would support a judgment in its favor on any theory.

The appellant also objects that, if the award is valid, it is a bar to the Government's counterclaim. But an examination of the award, which is set out in detail in the findings, shows that the award was concerned only with the first contract, of June 24, 1918, and that the items and computations which entered into it related only to that contract. The amount due from the Government upon appellant's note and second contract was unaffected by it.

There is no merit in the objection that the amount of the award should have been credited on appellant's note as of the date of the cancellation of the first contract, thus reducing the amount of interest payable on the note. If the award was valid, it was properly credited as of its

[blocks in formation]

date. If it was invalid, appellant, as already pointed out, has laid no foundation for any offset to the amount due on the note.

Judgment affirmed.

RISTY ET AL., COUNTY COMMISSIONERS, ET AL. v. CHICAGO, ROCK ISLAND & PACIFIC RAILWAY COMPANY.

THE SAME v. CHICAGO, MILWAUKEE & ST. PAUL RAILWAY COMPANY.

THE SAME v. CHICAGO, ST. PAUL, MINNEAPOLIS & OMAHA RAILWAY COMPANY.

THE SAME v. NORTHERN STATES POWER
COMPANY.

THE SAME v. CITY OF SIOUX FALLS.

THE SAME v. GREAT NORTHERN RAILWAY

COMPANY.

APPEALS FROM THE CIRCUIT COURT OF APPEALS FOR THE EIGHTH CIRCUIT.

Nos. 95-100. Argued January 7, 8, 1926.-Decided March 1, 1926. 1. When the District Court and Circuit Court of Appeals agree upon all material facts, this Court will consider them only so far as needful to pass on questions of law. P. 381.

2. The statutes of South Dakota (Rev. Code 1919, §§ 8458 et seq., §§ 8467, 8470,) contain no provision by which the cost of reconstructing or maintaining existing drainage works may be assessed on lands which were not embraced within or assessed in connection with the project as originally established. P. 383.

3. It is the duty of the federal courts, in suits brought in or removed to the District Courts, to decide for themselves all relevant questions of state law, including the meaning of the state statutes where they have not been clearly and decisively passed upon by the state court. P. 387.

[blocks in formation]

4. Questions involving the Federal Constitution, giving the federal court jurisdiction, need not be passed upon when the case is decided by applying the state law. P. 387.

5. Suits in the federal court to enjoin state officials from equalizing benefits of drainage work and making assessments of the cost, held not premature, but within equitable jurisdiction, where the ground of the suits was the invalidity of the whole proceedings, and not merely inequality in apportionment of benefits, and where the effects of the proceedings would be to establish liens on plaintiffs' lands, clouding the titles, and subject them to liability for future assessments. P. 387.

6. The remedy, in such cases, afforded by § 8465 of So. Dak. Code, 1919, does not appear to be coextensive with the relief afforded by equity. Id.

7. The test of equity jurisdiction in a federal court is the inadequacy of the remedy on the law side of that court, and not the inadequacy of the remedies afforded by the state courts. P. 388.

8. It does not appear that the law of South Dakota affords a remedy, in cases like the present, by payment of the assessment and suit to recover it back, which could be availed of in the federal court, or that such remedy, if available, would not entail a multiplicity of suits. P. 388.

9. Where the legal remedy under the state law is uncertain, the federal court, (having jurisdiction as such of the case,) has jurisdiction in equity to enjoin illegal assessments. P. 389. 10. Jurisdictional amount held involved in suits against a board to enjoin illegal apportionments and assessments of cost of drainage work, where the board had made tentative assessments against plaintiffs in excess of that amount, and the basis of the suits was want of jurisdiction to make such apportionments and assessments. P. 389.

11. Plaintiffs held not estopped to question the legality of proceedings to extend drainage assessments to their land outside the drainage area, because of their relation to the proceeding or to the construction before they had knowledge of the purpose so to extend the assessments. P. 389.

12. A bill by a city to restrain the laying of drainage assessments under a law of its own State, as violative of the Fourteenth Amendment, is too unsubstantial to confer jurisdiction on a federal court, since the Amendment does not restrain the power of the State and its agencies over its municipal corporations. P. 389. 297 Fed. 710, affirmed in part; reversed in part.

[blocks in formation]

APPEALS from decrees of the Circuit Court of Appeals, which affirmed decrees of the District Court (282 Fed. 364,) in favor of four railroad companies, a power company, and a city, in six suits brought by them to enjoin a board of county commissioners and certain state officers, of South Dakota, from extending apportionment of benefits and assessments of costs, of a drainage project, to outside lands.

Messrs. Benjamin I. Salinger, N. B. Bartlett, and E. O. Jones, for appellants.

Mr. Edward S. Stringer, for appellee in No. 95, submitted. Messrs. M. L. Bell, W. F. Dickinson, Thomas D. O'Brien, and Alexander E. Horn were also on the brief.

Mr. E. L. Grantham, for appellee in No. 96, submitted. Messrs. C. O. Bailey, J. H. Voorhees, T. M. Bailey, H. H. Field, and O. W. Dynes, were also on the brief.

Mr. C. O. Bailey, with whom Messrs. J. H. Voorhees, T. M. Bailey, Roy D. Burns, and R. L. Kennedy were on the brief, for appellees in Nos. 97 and 99.

Mr. R. M. Campbell, for appellee in No. 98, submitted. Messrs. Harold E. Judge and John H. Roemer were also on the brief.

Mr. Harold E. Judge, for appellee in No. 100, submitted. Mr. F. G. Dorety was also on the brief.

MR. JUSTICE STONE delivered the opinion of the Court.

Separate suits were brought by the several appellees, in the United States District Court for South Dakota, to enjoin the County Commissioners, the Auditor and the Treasurer of Minnehaha County, South Dakota, from making any apportionment of benefits or assessments of costs affecting the property of the several appellees, for

« ՆախորդըՇարունակել »